Title
RESOLUTION AWARDING A CONTRACT TO MINNCOMM UTILITY CONSTRUCTION FOR THE “LEAD SERVICE LINE REPLACEMENT - LONDON ROAD” PROJECT FOR A TOTAL AMOUNT NOT TO EXCEED $1,165,250.50.
Body
CITY PROPOSAL:
RESOLVED, that the proper city officials are hereby authorized to enter into a contract with MinnComm Utility Construction for the Lead Service Line Replacement - London Road project for a total amount not to exceed $1,165,250.50, payable from fund 510-500-1905-5533; UtilB-2305 (water; Public Works and Utilities; capital (incl deprec/debt svc); capital improvements - revenue; utility projects budgeted; 2305 London Rd LSLR). City project number 2305.
Statement of Purpose
STATEMENT OF PURPOSE: This resolution will authorize construction of the Lead Service Line Replacement - London Road project by MinnComm Utility Construction for a total amount not to exceed $1,165,250.50. The project will replace 45 public and private lead water services, replace 6 fire hydrants, and provide surface restoration along London Road between 26th Ave E and 60th Ave E. This project is planned to be completed prior to MNDOT’s resurfacing project along London Road in 2026. MinnComm Utility Construction was the lowest responsible bidder of the two companies that responded. The engineer’s estimate was $1,006,000.00. The City will be reimbursed by the Minnesota Public Facility Authority in the amount of $1,066,106.50 for the service work, and the water fund will pay for the hydrant replacements in the amount of $99,144.00.