Title: RESOLUTION AMENDING RESOLUTION 18-0060 APPROPRIATING AN ADDITIONAL $190,000 TO THE MINNESOTA DEPARTMENT OF TRANSPORTATION FOR COOPERATIVE CONSTRUCTION AGREEMENT NO. 1029895 FOR PAYMENT OF THE CITY'S SHARE OF CONSTRUCTION COSTS RELATING TO TH 194 (MESABA AVENUE) UNDER STATE PROJECTS 6933-95 AND 6933-97, CITY PROJECT NO. 1520.
Attachments: 1. 18-0586R Map

Title

RESOLUTION AMENDING RESOLUTION 18-0060 APPROPRIATING AN

ADDITIONAL $190,000 TO THE MINNESOTA DEPARTMENT OF TRANSPORTATION

FOR COOPERATIVE CONSTRUCTION AGREEMENT NO. 1029895 FOR PAYMENT

OF THE CITY’S SHARE OF CONSTRUCTION COSTS RELATING TO TH 194

(MESABA AVENUE) UNDER STATE PROJECTS 6933-95 AND 6933-97, CITY

PROJECT NO. 1520.

 

Body

CITY PROPOSAL:

RESOLVED, that the Minnesota Department of Transportation (MNDOT) is improving

TH 194 (Mesaba Ave), and as part of that project, is making improvements to city

utilities. MNDOT estimated the city’s participation at $100,396.80. The project was bid

at a higher amount than estimated, and further changes have resulted in increased

costs. This amendment increases the estimated city’s participation in the amount of

$190,000 to a new estimated total of $290,396.80.

 

Estimated construction and engineering costs from funding:

 

Street Lighting Utility Fund 550                      $275,777.10

Water Fund 510                                                                $4659.66

Gas Fund 520                                                                $873.69

Sanitary Sewer Fund 530                                           $3494.75

Storm Water Fund 535                                           $5,591.60

New Estimated Total:                                           $290,396.80

 

Statement of Purpose

STATEMENT OF PURPOSE:  MNDOT is improving TH 194 (Mesaba Avenue), to

include some city utility work within the corridor. The project costs have increased due

to higher bid prices than estimated, as well as additional work being added to the

contract.

 

As is the nature of rehabilitation projects, concrete and pavement removal limits

increased, resulting in the removal of 81 vehicle detection loops instead of the 4 that

were in the contract. A decision was made to switch to camera control, at a lower cost

than replacing all of the loops.

 

The emergency vehicle preemption system specification did not list the City of Duluth’s

GTT system, which then allowed for generics. In order for the new detection system to

work, a change was made to switch to what our Duluth’s system currently uses, at a

higher cost.

 

Painting of the five signal systems was included in this project, was budgeted in the

2018 Street Lighting Fund, but was left out of the MNDOT plans. This work is being

added to MNDOT’s contract with the contractor, at a negotiated price.

 

If these items had been included in the original plans and specifications, the city would

have been responsible for these costs. This amendment provides for the city to receive

the products and work we had originally intended.