File #: 19-0571R    Name:
Type: Resolution Status: Passed
File created: 8/15/2019 In control: Public Works and Utilities
On agenda: 8/26/2019 Final action: 8/26/2019
Title: RESOLUTION AWARDING A CONTRACT TO JMF CONSTRUCTION, INC. FOR THE 2019-2020 CITYWIDE MANHOLE ADJUSTMENT PROJECT IN THE AMOUNT OF $101,077.92.

Title

RESOLUTION AWARDING A CONTRACT TO JMF CONSTRUCTION, INC.  FOR THE 2019-2020 CITYWIDE MANHOLE ADJUSTMENT PROJECT IN THE AMOUNT OF $101,077.92.

 

Body

CITY PROPOSAL:

RESOLVED, that the proper city officials are hereby authorized to enter into a contract with JMF Construction, Inc. for the 2019-2020 Citywide Manhole Adjustment Project in the amount of $101,077.92. Payable equally out of Sanitary Sewer Fund 530 and Stormwater Fund 535, Department/Agency 035 (Capital Projects Accounts), Object 5535 (Non-Capital Improvements), city project no. 1855.

 

Statement of Purpose

STATEMENT OF PURPOSE:  This resolution authorizes the 2019-2020 Manhole Adjustment and Bollard Installation project by JMF Construction, Inc. in the amount of $101,077.92.  JMF Construction, Inc. was the lowest responsible bidder of the two companies that responded.  The engineer’s estimate was $150,000.  This project is for the adjustment of manholes that are failing or require maintenance. Payable equally out of Sanitary Sewer Fund 530 and Stormwater Fund 535, Department/Agency 035 (Capital Projects Accounts), Object 5535 (Non-Capital Improvements), city project no. 1855, requisition no. 19-99528. 

 

 

TABULATION OF BIDS RECEIVED AUGUST 15, 2019

JMF Construction, Inc.

Duluth, MN

$101,077.92

A Plus Landscaping, LLC

Saginaw, MN

$107,250.00

Northland Constructors of Duluth, Inc.

Duluth, MN

$112,350.00